Project BackgroundIt was at the Birkenhead Town Council meeting on the 11th of September 1940, that it was suggested that two large civillian air raid shelters could be built uner rock outcrops in Tranmere and Bidston.
Bidston Timeline- May 1941: Mr Kooyker, a mining engineer, employed for a period of four weeks to work on preperation for the Bidston Tunnel and this period extended by a further four weeks into June.
- December 1941: Excavation of the entrances and the construction of the magazince commenced.
- January 1942: Total excavated No.1 entrance 132ft & No.2 entrance 75ft. 45 men employed in this tunnel.
- February 1942: Total excavated 722ft. 60 men employed on this tunnel.
- March 1942: Total excavated 1292ft. 64 men employed here.
- April 1942: Total excavated 2051ft. 57 men employed on this tunnel. Decision that lining not necessary throughout the tunnel, but essential in certain places, and flooring to be provided throughout. Sand excavated from the tunnels to be stored on site of Rhododendron Gardens then sold for building purposes.
- June 1942: Total excavated 2882ft. Considerable difficulty met with faults in the rock. 62 men employed on this tunnel.
- July 1942: Progress hindered by roofing problems with an arched roof in places being considered. Estimated cost increased o £15.8.0 per head.
- August 1942: Decision to introduce an arched roof section in certain places to reduce the amount of structural lining. Estimated cost now £46,672 with an estimated 2,213 bunks and 793 seats. Cost now £15.11.0 per head with difference between original of £13.5.0 per head to be drfrayed by the Corporation. 42 men employed here.
- October 1942: The whole of the arch trimming complete; a number of bunks installed. 41 men employed here.
- January 1943: A report said that due to the unreliable nature of the rock, which was not apparent until it had been exposed to the air for considerable period and having to arch the roof throughout, the cos was now estimated at £51,000. To increase the maximum number by 700 could be achieved by adding an additional tier to the three-tier bunks at a cost of £1.00 each. It is noted that the quality of the unskilled labour available at Bidston is markedly inferior to that at Tranmere.
- March 1943: The excavation of Bidston was relatively cheaper than that of Tranmere due to the softness of the rock and hence reduced labour costs; lesser volume of explosives required; Bidston soil was tipped close to the entrance whereas at Tranmere, 25,000 tons have to be loaded and transported off site.
- June 1943: Final bill for the Bidston Deep Shelter settled at £48,000 of which £6,510 was the liability of the Birkenhead Corporation.
- March 1944: Official number of bunks erected stands at 1,596 (from the intended total of 2,136).
- April 1944: Since the completion of the Bidston Deep Shelter, approx 950 tons of surplus sand sold to M/s Tilston & Roberts at 1/- per ton - 19,000 tons remaining.
- May 1945: Request from Robertson & Buckley & Co to use the shelter as a storage area for raw materials.
CreditsExtract taken from the following book:
Title: Wirral On The Home Front 1939-45
Author: Ian Boumphrey
ISBN: 1-899241-24-8
Price: £11.95
Order:
http://www.yesterdayswirral.co.uk/